Here’s where the gas upgrade works in Truro will be over the next few weeks

Works to ensure that gas flows to heat local homes and power businesses began in Kenwyn Street on January 2, 2025.

Now, barring any engineering difficulties, Wales and West expect to be finished in the area by the start of May.

A spokesperson said: “We appreciate that businesses will be concerned about the disruptions and required traffic management that will be in place while Wales and West undertake their work.”

The team on site’s work is on schedule which means the current planned traffic management is as follows:

February 3 and March 5

Little Castle St will be closed from the junction of Kenwyn Street to the junction of River Street. Kenwyn Street will be closed from Victoria Square to the junction of Little Castle Street.

March 3 and April 7

Victoria Square will be closed from the junction of Kenwyn Street to the junction of River Street. St Nicholas Street will be closed from the junction of Victoria Square to the junction of King Street.

River Street will be closed from the junction of St Nicholas Street to the junction of Castle Street.

March 31 and May 2

Calenick Street will be closed from the junction of Kenwyn Street to the junction of Moorfield car park.

April 14 to May 2 

Infirmary Road closed from the junction of Charles Street to ‘Lysnoweth’, with traffic lights on City Road, Charles Street and Calenick Street.

Traffic management will be signposted. Dates and durations are subject to change due to engineering progress.

If you have any questions, we encourage businesses to liaise directly with the Wales and West teams on-site.

Or contact their Customer Service Team on freephone 0800 912 2999.